Reconstruction of administrative buildings
AB Na Pankráci 58, Prague 4
- Restoration of information and communication technologies, interiors, social facilities and facades took place in 1998
- The objective of the reconstruction was construction of reliable foundations for infrastructure for companies which will have a new place of work in the reconstructed object
- Total costs for reconstruction amounted to CZK 29 million
AB Vyskočilova 3/741, Prague 4
- Current capacity is 268 offices including 71 reserved parking places
- Complete reconstruction was divided into several phases and it was taking place in the period from 1998 to 2000
- Total costs for reconstruction amounted to CZK 63 million
AB T.G.Masaryka 18 (Karlovy Vary)
- Reconstruction was completed in 1995
- The administrative building is situated in the center of the commercial part of Karlovy Vary
- Present-day office premises – large-area offices
- Total costs for reconstruction amounted to CZK 150 million